Cost: Cash Flow Forecasting

Access a project-level cash flow analysis and quickly visualize the difference between planned actual and forecast with built-in dynamic charts to ensure plans are being met, risk is mitigated, and profit is maximized.

Setting Preferred Forecast Period

  • Within Settings Admins can set preferred forecast periods; weekly or monthly. Once a forecast distribution is created on any budget item this setting cannot be changed.

Built-In Forecast Distribution Curves

  • Perform forecast distributions for each budget line item with four built-in forecast distribution curves, including front-loaded, rear-loaded, typical, and linear (when required, you can manually override).
  • There are three ways to access the distribution curve functionality.

 

    • OPTION 1: Via the Forecast Distribution section of the budget item’s details flyout panel.

Option 1

    • OPTION 2: Within the Forecast Tool via the more menu (three-dot menu) of a budget line item in the Cost & Time view.
      • From this view you can also select multiple budge items and batch create forecast distributions.
      • If you use a grouped view (via. filters) you can multi-select by the group header.

Option 2

Page break

    • OPTION 3: Within the Forecast Tool via the more menu (three-dot menu) of a budget line item in the table in the Cashflow view.

Option 3

  • A Create Forecast Distribution dialog box will appear when creating a forecast distribution, add in the distribution start and end date. When performing distributions to items connected to the schedule, dates automatically pull in. 
  • Choose the Curve from the drop-down menu; front-loaded, rear-loaded, typical, and linear. Note, a Budget with a time-based unit can only be distributed with a linear curve.
  • Select, Create. 
Page break

  • The details flyout panel will update to display a graphic representation of the distribution
  • Choose to display the information by amount or percent. 
  • Select the three dot more menu to delete the distribution.
  • Use the control icon to access the chart’s settings to display the chart by period, cumulative, or cumulative & by period. 
  • Select the arrow icon to expand the chart view. 

  • Note: Work Completed and Actual Cost is automatically added into the distribution if Revised Budget and Forecast Final Cost has not been distributed.
    • This information comes from this forecast distribution date.
    • By default, it comes from the date the item was approved, but you can edit it.

  • Hover over a specific point on the chart to view detailed information. 
Page break

  • In the table, scroll to view the distribution periods.
  • As projections are made, the system will auto-flag if the distribution total doesn’t match the forecast-final cost and direct you to open the distribution details.

  • The distribution details will open in the Cash Flow tab.
  • There you can manually make the distribution.

  • To customize the distribution further, select the more menu to add periods or delete the last period.
Page break

Project Level Cash Flow Analysis

  • Once all budget line items are forecasted, teams can access a project-level cash flow analysis to easily visualize the cash flow distribution throughout the project lifecycle.
  • This real-time summary enables teams to see planned actual and forecast quickly. It also provides the ability to drill into details if needed.
  • To access this, open the Forecast tool via the left sidebar then, select the Cashflow tab.

Time-Versus-Money Chart Navigation

 

  • To display the built-in dynamic time-versus-money chart, select the chart icon.
  • Click Revised Budget, Work Completed, Actual Cost, or Forecast Final Cost to switch between views. 
  • Choose to display the information by amount or percent. 
  • Use the control icon to access the chart’s settings to display the chart by period, cumulative, or cumulative & by period. 
  • Hover over a specific point on the chart to view detailed information. 

Table Navigation

 

  • Use the control icon to rearrange columns and hide/show months. 
  • Use the filter icon above the cart to filter/group the information within the table. 
  • To save views, select Default View, then Save Current Views. 
Page break

  • To dive deeper, hover to the right of the line item’s name to access the option to open details view. 

  • With the details view open, select the name of a budget item to view specific information/make updates within the details flyout panel. The graph will also change to display the information relevant to that item for the particular view you’re in. 
  • To delete distribution directly from the table select the three dot more menu.
Page break

Forecast Distribution Date in Details Flyout Panel

  • When a budget payment application, cost payment application or expense is approved, the ‘Forecast Distribution’ date field within the details flyout panel will display the same date as the ‘Approved’ date.
  • However, it can manually be modified manually to meet your needs.