Cost Management

Improve cost control, gain real-time visibility of cost-related risks, and forecast accurately by centralizing all cost activities in the cloud and within the context of the project. 

Introduction

Overview

Tracking costs, managing risk, and keeping a project on budget can be one of the biggest hurdles in a construction project. Finding efficiencies in this area can make all the difference in delivering a project on time and on budget.

BIM 360 Cost Management’s functionality enables teams to reduce risk by managing all cost-related activities in the cloud with streamlined and connected workflows. Teams gain real-time visibility into cost-related risk, the ability to forecast accurately, and greater accuracy on cash flow and profitability projections.

The following guide introduces suggested cost management workflows and gives context to the different capabilities built into the product, including step-by-step starter guides.

 

Visit BIM 360 Help Site

Suggested Workflows

Cost and Change Management Workflow

Used to help control cost and confirm all changes are accounted for and managed effectively to maintain positive cash flow, reduce risk and maximize profit. The graphic below outlines the suggested cost and change management workflow using Autodesk Build.

Why follow this workflow?

  • Customizable to suit users needs and preferences
  • Provides a real-time summary view of all budget items and contracts
  • Streamlines upstream and downstream change order workflows

Capabilities Used

  • Budget management
  • Contract management
  • Change order management
  • Payment applications
  • Forecasting
  • Actuals

Payment Application Workflow

Used to help manage incremental pay applications effectively to automate tasks and gain a real-time view of the project’s financial health. The graphic below outlines the suggested pay application workflow using Autodesk Build.

Why follow this workflow?

  • Adds a level of automation
  • Easy to manage and track
  • Provides a real-time summary view of all cost and budget payments

Capabilities Used

  • Budget management
  • Contract management
  • Budget payment applications
  • Cost payment applications
  • Document generation

Cost Management Capabilities

Home Page

The Cost Management home page provides a quick overview of the financial status of your project. Data is automatically collected and calculated, and is displayed in graphs. Click here to learn how to personalize the Home page.

Calendar View Overview

  • The calendar displays an aggregated view of project-level dates.
  • Use the arrows to scroll or the drop-downs to navigate between different months and years.
  • Click “Day” or “Week” to toggle between the different views.
  • Select the hyperlink within the listed item to open it (permission permitting).

Managing Dates within Settings

  • Dates are managed by Admins within Settings.
  • In Settings navigate to the Dates section in each component (e.g., Cost).
  • For editable dates, select the three-dot menu.

Date Types & Display

  • Non-editable system generated dates – Are not displayed 
  • Editable system generated dates – Display can be turned on or off
  • Custom dates created within Custom Attributes – Display can be turned on or off

Relative Dates

  • Leverage the relative date option for cases where an activity is relative to the date of another activity (e.g., creating a procurement schedule).
  • The relative date option is only available for editable system generated dates and custom dates.

Budget Chart

  • This section contains several pie charts that display the percentage of money in each budget relative to the total project amount. Click a budget name to show or hide it from the chart. Click the gear icon to check when the chart was last updated. The available views in this section are:
    • Original Budget – This chart shows the budgets in your project based on their original value, which was added when the budget was created. This data is collected from the Original Budget column in the Budget tab.
    • Revised Budget – This chart shows the sum of the Original Budget, Internal Budget Transfer, and Approved Owner Changes columns for each budget in the project and how it relates to the total project. This data is collected from the Revised column in the Budget tab.
    • Projected Budget – This chart shows the sum of the original budget, approved, and pending changes for each budget in the project, presented as a percent. This data is collected from the Projected Budget column in the Budget tab.
    • Original Commitment – This chart shows either the anticipated or contracted amount for the relevant supplier scope. This data is collected from the Orig. Commitment column in the Budget tab.
    • Forecast Final Cost – This chart shows the final projected cost as the sum of the projected costs and forecast adjustments. This data is collected from the Forecast Final Cost column in the Budget and Contract tables.

    Each pie chart presents the amount of money in each budget as a percentage of the whole project, where several budgets exist.

    Note: This chart is only visible to members with Budget View All or Full Control permission.

Budget and Cost Trend Chart

  • The Budget and Cost Trend Chart provides a quick and easy way to track changes in your project’s budgets and cost over time.
  • Toggle items in the chart legend (Original Budget, Revised Budget, Original Commitment, Forecast Final Cost) of a bar chart or pie chart to choose what to display in the card.
  • To permanently save a view of the card, modify it in the Customize mode and click Save.

Reviews Chart

The Reviews Chart displays current active workflows, review step, reviewer, and due date for all custom approval workflows.

 

  • You can expand the view of the chart, via the expand arrow on the right.
  • Quickly access Items in the chart via a hyperlink, permission pertaining.  
  • To keep track of all items by the same reviewer, filter by reviewer via the filter icon on the right.  
  • If the due date appears in red color, it means an item is past due.

Settings and Permissions

BIM 360 Cost Management is flexible and customizable. Configurable features allow teams to customize the software to suit their needs and preferences. Teams can also ensure the right information stays in the right hands by setting permission levels for each component within Cost Management.

1. Activate the Cost Module

  • A Project Admin needs to activate the Cost Management module for project members.
  • Within the Project Admin module, select the Services tab, then the Activate button for Cost Management.

2. Accessing Settings

  • Project Admins are the only individuals who have permission to access and edit the settings for Cost Management.
  • In the Project Admin module, select the “Services” tab. On the left sidebar select Cost Management to access the general settings and settings for each tool (e.g. Change Order).

3. General Settings

Select the “General” tab.

  • Project Process: An optional setting that configures which components in Cost Management display and configures permission options based on selected role and project preferences.
    • By using Project Process, teams have the option to enable a collaborative Potential Change Order workflow for upstream and downstream change orders. It is made of 3 main optional Project Process driven features.
      • A user can let their supplier generate PCOs and have them reviewed/rejected.
      • A user can send a PCO out to request pricing for a change order instead of using RFQ (assuming only one recipient in the PCO).
      • A collaborative PCO workflow where the GC can directly submit a PCO rather than COR to the customer and have the owner review/accept/reject.

  • Unit of Measure: Select imperial or metric.
  • Unit of Measure List: Set specific dimension as default or deactivate certain units from the list. Click “Add” to manually add additional dimensions.
  • Companies Setup: Identify the project Owner, General Contractor, and Architect. Use the drop-down to select the correct contact or add a new contact.

  • Budget and Contract Allocation: Allow the ability for project members to allocate a budget to multiple contracts.
  • Round Settings: Select the “Rule” (Half up, Round up, Round down) and “Accuracy” (1, 0.1, 0.01, 0.05). In the example field, users can test the settings.
  • Retention: Allows users to put in a default retention percent for completed work and materials on site. This will automatically be added to every line item, but can be edited/removed per line.

  • Document and Attachments: Allows users to choose to store generated documents and uploaded attachments in both Cost and Autodesk Docs. Choosing to store the files in Autodesk Docs creates a single repository of all generated documents specific to each company for future audit purposes. If desired, the folder can be shared with other project members to access the information.
  • Work Schedule: Allows users to set a default number of hours worked per day and days of the week.
  • Tab Names & Order: Allows users to customize the names of the main tabs (Budget, Cost, Change Order) and the subtabs within each (e.g. Cost Item, PCO, RFQ, etc.) to better suit users’ needs. To change the display order of the subtabs in each section, select the three dots.

4. Budget Settings

Select the “Budget” tab.

  • Budget Code Segments: Used to set up the Budget Code template. Refer to the Budget Code Setup chapter for more details on setting up the budget.
  • Budget and Contract Allocation: Allow the ability for project members to allocate a budget to multiple contracts.
  • Round Settings: Select the “Rule” (Half up, Round up, Round down) and “Accuracy” (1, 0.1, 0.01, 0.05). In the example field, users can test the settings.

  • Budget overview columns: Used to create custom calculated budget columns.
  • Lock Budget: Once the original Budget Setup is finalized, lock it to avoid accidental change.
  • Allow Internal Budget Transfer: Turns off the ability to allow users to make an internal budget transfer from the budget summary view.
  • Main Contract Schedule of Values: Choose how Change Orders should display – as a line item, or in a column.

As with all our custom lists, system defaults cannot be deleted, but they can be deactivated so they will not show up in the user interface.

  • Main Contract Types: Use the “Add” button to create a list of main contract types. This is the primary contractual agreement entered into directly; for example, between an Owner and a General Contractor. In edit mode in the Main Contract tab, users can assign a contract type to a line item via a drop-down.

  • Document Templates: Use to create standard Budget Payment Application and main contract template formats, the templates are created using fields that automatically populate with data from the system. Refer to the Document Templates section to learn how to create Document Templates.
  • Custom Attributes: Use to customize portions of the details flyout panel for items in each subtab within the Budget tab. Refer to the Custom Attributes chapter to learn how to create Custom Attributes.
  • Default Email Message: Use to create custom default email messages for when a Budget Payment Application is sent.

5. Budget Overview Columns

  • In the Budget settings within the Budget overview columns section, Project Admins can manage the name, group and order of existing columns. As well as create custom columns calculated on base values or other columns.
  • To manage existing columns and create custom calculated budget columns, select the “Manage” button.

Managing Existing Columns 

  • To change where existing columns appear (group and position), rename them and control which appear by default. Select the column name and choose the desired option beneath the list view.

Creating Custom Calculated Columns 

  • Duplicate an existing column and edit the formula by selecting the column name, then the “Duplicate” button. To create a new column from scratch, select the “Add new” button.
  • Example: Creating a column next to Approved Change Orders in the Cost group titled Recoverable Change Orders shows what will be paid for by the Owner.

  • How It’s Done:
    1. Select “Add new”.
    2. Update the column name.
    3. Choose the column group.
    4. From the left side panel, drag and drop to add the formula item.
    5. On the right side panel, select the value type and enter a value to preview.
    6. Drag additional formula items as needed and update values.
    7. Update the column position and visibility option.
    8. Select “Save”.

6. Cost Settings

  • Select the “Cost” tab.
  • Number Format: Ability to configure the expense code format by customizing the prefix, suffix, number of digits, and start number. Ability to also include the type in the prefix.

  • Contract Overview Columns: Used to create custom calculated contract columns. Functionality to create and manage columns is similar to the budget overview columns, refer to the above section for more details.
  • Contract Types: Use the “Add” button to create a list of contract types. In edit mode in the Contracts tab, assign a contract type to a line item via a drop-down.

  • Expense Types: Use the “Add” button to create a list of expense types. In the Expense tab, assign an expense type to a line item via a drop-down.

  • Contract Approval Workflow: Used to create custom approval workflows to automate the routing of contracts for internal review.
  • Document Templates: Use to create standard Cost Payment Application and contract template formats, the templates are created using fields that automatically populate with data from the system. Refer to the Document Templates section to learn how to create Document Templates.

  • Custom Attributes: Use to customize portions of the details flyout panel for items in each subtab within the Cost tab. Refer to the Custom Attributes section to learn how to create Custom Attributes.
  • Default Email Message: Use to create custom default email messages for when Contracts and Cost Payment Application are sent from the system.

7. Change Order Settings

  • Number Format: Users have the option to configure the code format by customizing the prefix, suffix, number of digits, and start number for each component. This will dictate how the information is displayed in the number column of each tab within Cost. Users can also choose to use Change Order type and Contract code in the coding structure to provide easy grouping and filtering.

  • Financial Markup Formulas: Where users can create multiple project-level markup configurations to apply to Potential Change Orders (PCOs), Requests for Change Orders (RCOs), or Owner Change Orders (OCOs). Refer to the Financial Markup Formulas chapter to learn how to create custom Markups.
  • Change Order Types: Use the “Add” button to create a list of Change Order types. This allows them to be grouped by type and, if preferred, have different numbering schemes per type.

  • Cost Item Types: Use the “Add” button to create a list of Cost Item types. In the Cost Item tab within Change Orders, users can assign a Cost Item type to a line item via a drop-down list.
  • PCO Source Types: Use the “Add” button to create a list of PCO source types. In the PCO tab within Change Orders, users can assign a PCO source type to a line item via a drop-down list.
  • OCO & SCO Approval Workflow: Used to create custom approval workflows to automate the routing of SCOs and OCOs for internal review.

  • Document Templates: Used to create standard template formats for PCOs, RFQs, RCOs, OCOs, and SCOs. The templates are created using fields that automatically populate with data from the system. Refer to the Document Templates section to learn how to create Document Templates.

  • Custom Attributes: Use to customize portions of the details flyout panel within the Change Order tab. Refer to the Custom Attributes section to learn how to create Custom Attributes.
  • Default Email Message: Use to create custom default email messages for when PCOs, RFQs, RCOs, OCO, and SCOs are sent from the system.

8. Permissions

  • Select the “Permissions” tab. Designate user-, role-, or company-based permissions for each tab within Cost Management. Auto permissions for each tab using role-based settings can also be set. Permission levels are:
    • No Access: can’t access the tab
    • Collaborate: can view and edit limited attributes of items assigned to them in the tab
    • View All: can view all items within the tab
    • Full Control: can view and edit all attributes on all items within the tab
  1. Use the search field to find the desired user, company, or role.
  2. Click “Add”.
  3. Hover over the permission level and click to access the menu drop-down. Set the appropriate permission level for each column.

Owner and Supplier Access 

 

  • To help streamline workflows and enhance collaboration with Owners and Suppliers, give them Collaborate access to view and interact with certain information.
  • The Collaborate permission is available for specific components within Cost and allows them to only view and edit limited attributes on items assigned to them. Note, an Autodesk Build license is required.

What Owner/Supplier with Collaborate permission can do

Related tab and component in Cost Management

Supplier Request for Quotation

 

  • Provide work breakdown and propose a price
  • Upload/download attachments

Change Order Tab

RFQ Component

Owner Request for Change Order

 

  • Accept or reject RCO
  • Download RCO documents
  • Upload/download attachments

Change Order Tab

RCO Component

Owner Change Orders

 

  • Approve or reject OCO
  • Download OCO documents
  • Upload/download attachments

Change Order Tab

OCO Component

Supplier Payment Application (with view and respond access)

  • Fill in pay application and submit to contractor
  • View previous applications
  • Generate payment application documents
  • Upload/download attachments

 

Supplier Payment Application (with create, view, and respond access)

  • Create new billing periods in contract and cost payment application views
  • Set due dates
  • Fill in pay application and submit to contractor
  • Delete a payment application with the status of Submitted, Revised and Resubmitted, or Pending Supplier Input. Can’t delete a payment application with the status of In Review, Accepted, Approved or Paid.
  • Delete billing period if no linked payment application
  • View previous applications
  • Generate payment application documents
  • Upload/download attachments

Cost Tab

Cost Payment Application Component

Owner Payment Application

 

  • Approve or reject pay application
  • View previous applications
  • Download payment application documents
  • Upload/download attachments

Budget Tab

Budget Payment Application Component

Supplier Contract Exhibits/Attachments

 

  • Upload/download

Cost Tab

Contract Component

Supplier Schedule of Values

 

  • Provide schedule of values breakdown

Cost Tab

Contract Component

Budget Code Setup

BIM 360 Cost Management is flexible and customizable to meet your needs and preferences while also giving you the freedom to slice and dice your data.

1. Accessing the Budget Code Settings

Project Admins are the only individuals who have permission to access and edit the Budget Code.

  • In the Project Admin Module, select Services and then Cost Management on the left sidebar.  
  • The Budget tab is where the Budget Code is set up. 

PRO TIP: The tab name ‘Budget’ can be customized within General Setting.

2. Budget Code Template

Budget codes are generally made up of individual segments of information, such as a work classification, sub job, cost type, etc. Some companies have only one segment, and some have multiple. Cost Management does not have limits. During the budget setup process, define the number of segments for your codes (see section 3) and each segment’s length. The sum of the segment lengths equals the total length of the budget code.

  • Within the Budget tab, you can either build the Budget Code format from scratch, import an Excel list from an accounting system, or integrate it directly into the system via API from ERP/Estimating system or similar.
  • This informs the system how the Budget Code should appear in Cost Management. 

Budget Import 

 

  • The imported budget should not include summary groups of other budget items, as shown in the left screenshot below. Grouping is managed by using master lists for each segment, allowing the budget to be sliced and diced in many different ways, as described in sections 36 on the following pages.  
  • There is a concept of sub-items in the budget, which allows for a budget item to have cost build-ups. But they should only be build-ups relative to the actual budget item. 

Importing Special Characters

 

  • When importing budget codes the system allows the import of special characters (e.g, hyphen), known as a delimiter within the actual imported code.
  • Any special characters will be counted in the # of digits in the segment. For example:
    • 03.00.00 = 8 digits
    • 030000 = 6 digits

 

  • Users can add delimiters between complete segments. For example, if CSI was a segment (8 digits) and cost type another (3 digits) then there might be a delimiter between 03.00.00-LAB. This example will be 11 total digits (8+3) when imported.
  • This means both the group headers which are driven by the segment master list and the actual budget line items will be shown with special characters.

3. Creating Budget Segments

  • In the Segment section, double-click to rename the sample segments and select Add new to add additional segments.  
  • At a minimum, there must be least one segment, but multiple segments can be created as required. 
  • Click and drag the segment tabs to rearrange.  

4. Adding Budget Segment Details

  • “Where” informs the system how to show the segment: 
    • Code  as part of the whole Budget Code. 
    • Column  in a separate column from the Budget Code. 
    • Info only – purely for information and not shown in the budget columns. 
  • “# of digits” informs the system how many digits are expected for that segment. 
    • For irregular structures, choose Variable Length for the segment’s # of digits.
    • Variable Length can be applied to multiple segments and the max # of digits per individual segment is 20.
  • “Delimiter” informs the system how to separate the segments, if at all. When importing budget codes the system allows for the import of special characters (e.g, hyphens, periods, etc), which is known as a delimiter.

PRO TIP: You can’t edit segments when there are budget items in the project.

5. Adding Segment Values

  • Segment values can be added individually by selecting “Add” or by importing a master list.

Importing a master list:

 

  • When importing, users can either drag and drop or select “Import” to browse for an Excel sheet (must be .xls or .xlsx and can’t exceed 10MB). Note, only the first sheet in the workbook will be imported. 
  • Best practice, when importing a list, is to first download the template by clicking “Download template”. 
  • Hierarchy levels are unlimited. Child levels don’t require a column header; just insert a column for each level of hierarchy between “Code” and “Description” columns in the template. 
  • Every line item can have only one code. When importing, make sure to set # of digits” correctly, or an error message will display. 

  • Adding a master list of values for each segment is not a system requirement.  
  • However, if more detail is added into the budget segments (e.g. cost type, sub job, custom attributes, etc.), it can be used for grouping. 

6. Deleting Segment Values

  • To delete a segment value, select the checkbox next to the line item. Under “Segment code master list”, the “Add” button will turn into “Delete”. Select “Delete”.  
  • To delete all items, select the checkbox in the header row. 

7. Code Preview

  • The “Segment code preview” field allows users to input example data to confirm the segment code details are accurate.  
  • “Budget code preview” displays a preview of the entire Budget Code as it will be shown in Cost.  
  • Hover over the “Budget code preview”. A “Full code preview” pops up to display the code as it might look when imported into the system from your accounting system. 

Custom Attributes

The details flyout panel allows users to quickly view detailed information behind any item in multiple components within Cost Management. With the Custom Attributes feature, teams can customize a portion of the details flyout panel to suit their needs and preferences. 

1. Accessing Custom Attributes

  • Project Admins are the only individuals who have permission to create and edit Custom Attributes.  
  • Within the Project Admin module, select Services then Cost Management on the effete side bar. You will now be able to access the settings for the different components within Cost.  
  • Custom Attributes can be created in the following tabs for each component: 
    • Budget: Budget, Main Contract, and Budget Payment Application 
    • Cost: Contract, Cost Payment Application, Expense, Expense Subitem 
    • Change Order: Cost Item, PCO, RFQ, RCO, OCO, and SCO 
  • Note, the main tab and component names can be customized within General Settings. 

2. Creating Custom Attributes

  • To create a Custom Attribute, hover over the component and select “Add”.

  • Either click to add, or drag and drop the attribute from the left sidebar into the center preview panel.
  • Select the attribute to define it in the properties panel on the right. 
  • Rearrange the attributes by clicking then dragging and dropping the field. Select “Finish” when done. 
  • The attributes will appear in the component. Like adding, click to edit. 

  • Some custom attributes generate a custom variable that can be referenced in documents. Not all custom attributes create custom variable entries. The following support custom variables:
    • Cost contract custom attributes
    • Change order custom attributes
  • The format for these custom attributes is {xxx.properties[“Attribute Title”]}.
    • For example: A date custom attribute for an RFQ titled “Required on Site” would be {rfq.properties[“Required on Site”]} would return the date specified.
  • Copy the variable from the custom attribute edit and paste it into the desired document template.

3. Viewing Custom Attributes in Item Details Flyout

  • Select an item within any of the Budget, Cost, or Change Order tabs. The details flyout will appear. 
  • In the details flyout, scroll down to the Custom Attributes section.  
  • This will display the Custom Attributes created in Settings. 

PRO TIP: Add Custom Attributes to the table view via the Control icon. In the table view, users can assign them. Users can also use Custom Attributes for grouping and filtering. To do this, select the filter icon, and then choose the attribute from “Group items by drop-down”.

Document Templates

Easily create standard documentation formats for distribution with Cost Management’s Document Templates capabilities. Templates are created using fields that are automatically populated with data from the system when generated.

1. Accessing Document Templates

  • Project Admins are the only individuals who have permission to create and edit Document Templates.
  • Within the Project Admin module, select Services and then Cost Management on the left side bar. You will now be able to access the settings for the different components within Cost.
  • Document Templates can be created in the following tabs for each component:
    • Budget: Main Contract, and Budget Payment Application
    • Cost: Contract, and Cost Payment Application
    • Change Order: Potential Change Order (PCO), Request for Quotation (RFQ), RCO, OCO, and SCO
  • Note, the main tab and component names can be customized within General Settings.

2. Downloading a Sample Template

  • Within the Document Templates section, select the component to add a template to.
  • Select “Download sample template” to automatically download a template. Depending on the component, you will have the option to download a Word or Excel template.

  • The downloaded template can be customized to suit the user’s needs.
  • Note, the content within the brackets must stay the same for the module to recognize and to auto-populate it when generating the document.

 

Document template variable details

PRO TIP: To remove “SAMPLE” click into the document header

  • Payment application document templates include additional rows in the payment details table to allow users to define hierarchy and parent node background color and font.
  • Summaries can be at the top or bottom of a document. Increasing the visibility of summary items within generated payment applications.

3. Uploading a Document Template

  • There are two ways to upload a document template:
    • Option 1: Drag and drop the file, or click “Browse” to locate the file on your computer for upload.
    • Option 2: Select a document from Autodesk Docs by clicking “Select files Autodesk Docs” and navigating to the correct folder.
  • Select “Finish” to save and exit.

4. Online Document Review Functionality

  • Once the document template(s) are uploaded to the system, Admins with Microsoft Office 365 can click on the desired template to open it online and make edits versus downloading a copy and re-uploading it. 
  • Users with Microsoft Office 365 can also open and edit Microsoft Word/Excel documents online directly from the document package section within the item’s flyout panel.

Financial Markups

Easily create multiple project level markup configurations to apply to Potential Change Orders (PCOs), Requests for Change Orders (RCOs), or Owner Change Orders (OCOs).

1. Accessing Financial Markups

  • Project Admins are the only individuals who have permission to create and edit financial Markups.
  • Within the Project Admin module, select Services and then Cost Management on the left side bar. You will now be able to access the settings for the different components within Cost.
  • Financial Markups are created in the Change Order tab.
  • Multiple Markup formulas can be created, and any existing formulas will be available in the list.
  • Use the drop-down to choose if the markups will be used in Budget or Cost changes. When Cost change is selected, it will enable the markups to display on the supplier change order page.
    • Budget change markups can be applied to either PCOs, CORs, or OCOs.
    • Cost change markups can be applied to either PCOs, RFQs, or SCOs.
  • Note, the main tab and component names can be customized within General Settings.

2. Creating a Financial Markup

  • Scroll to the Financial Markup Formulas section, and select “Add”.
  • Select the top “New formula” field to title the formula.
  • To add a description, select the pencil icon next to “New financial markup formula.”
  • To enter a sample cost basis, which will allow you to check the calculation as you start building the formula, select the pencil icon next to “Sample cost basis”.

Creating the Formula:

 

  • 1: Click “Markup” to add a new markup row to the formula, or select “Markup” and drag it into the center preview panel.
  • 2: In the Markup edit panel, name the Markup (e.g. Fee).
  • 3: Select the Markup type and amount:

 

    • “Percentage” for a standard percentage based markup.
    • “Flat” for a flat fee, per PCO.

 

  • 4: Select the “Cost basis” from the drop-down.
  • 5: Add a description of the Markup (optional).
  • 6: Search or scroll to select a target budget item for the Markup.
  • 7: By default, Markups are calculated on all budget items. Using the “Calculate on” fields, you can enter rules to only calculate on particular Budget Codes, Cost Types, etc.

  • 8: Add a subtotal by selecting “Subtotal” or by dragging it into the center preview panel.

 

    • Name the subtotal (e.g. Contingency and Fee).
    • Select the appropriate “Cost basis revising” option.
      • “Revise cost basis” (default), if revising the cost basis for all subsequent Markups, will be included.
      • “Info only” to summarize any Markups above for information.

 

  • 9: Select “Save”.

Custom Tax Calculations

Utilize the custom tax calculation feature to calculate taxes in all cost processes and show tax in the generated cost documentation to comply with government requirements.

1. Accessing Tax Calculations

  • Project Admins are the only individuals who have permission to create and edit tax formulas.
  • Within the Project Admin module, select Cost Management on the left side. You will now be able to access the settings for the different components within Cost Management.
  • Tax formulas are created and managed in the General Settings tab.
  • Multiple tax formulas can be created, and any existing formulas will be available in the list.
  • The tax formulas created here can then be applied to contracts, payment applications, and change orders.
  • Note, the main tab and component names can be customized within General Settings.

2. Creating a Tax Formula

  • Scroll to the Tax Formulas section, and select “Add”.
  • To the right, use the text field to name the formula.
  • Select the pencil icon next to the formula name to edit the name.

  • To update the net total default (1,000.00) in the center preview panel select “Net total”.
  • Click “New tax” to add a new tax row to the formula, or select “New tax” and drag it into the center preview panel.
  • In the Tax edit panel, name the Tax (e.g. VAT) and add the tax rate percent.
  • Taxes can be added, removed, named and re-ordered as required. After setting the tax rate for each, the amounts are calculated on the shown “Cost Basis”.

  • For situations where tax on tax is needed, create a single formula that includes multiple taxes by adding subtotals.
  • Add a subtotal by selecting “Subtotal” or by dragging it into the center preview panel.
  • In the Subtotal edit panel, select the appropriate “Cost basis revising” option.
    • “Revise cost basis” (default), creates a subtotal and recalculates the sample “Cost Basis” for subsequent taxes.
    • “Info only,” creates a subtotal for information purposes without recalculating the “Cost basis” for subsequent taxes.
  • Select “Save”.

  • To show tax in the generated cost documents, the document template will need to be updated with the new template available in settings.

3. Applying Tax

  • Tax can be applied to contracts, payment applications, and change orders via the details-flyout panel.
  • In the details-flout panel scroll to Tax and select “Apply Tax”.
  • All tax formulas will appear in the drop-down, select the appropriate formula.

  • Once selected, the tax summary will automatically appear.
  • Select the “More” menu to delete the tax or edit tax details.

  • Editing tax details allows you to remove tax from specific line items (e.g. tax exempt items).
  • In the edit tax details dialog box, click the check mark next to the item to remove the tax.
  • Select “Done”.
  • The change will automatically update in the Tax summary table.

4. Edit and Manage Tax Formulas

  • In General Settings scroll to the Tax Formula drop-down.
  • To edit a formula, select the formula name.
  • For additional options select the “More” menu to access the following options:
    • Duplicate: to make a copy of the formula.
    • Deactivate: to deactivate the formula so it won’t be used.
    • Delete: to permanently delete the formula
  • Note, tax formulas that have been applied to items can not be edited, deactivated, or deleted.

Custom Approval Workflows

Utilize a decision-based workflow engine to create custom approval workflows for Owner Change Orders (OCOs), Supplier Change Orders (SCOs), Contracts and Subcontractor Payment Applications. Structuring approval workflows will ensure contractually binding documents follow required internal review processes and allow for consistency and transparency of company-defined processes across projects.

1. Accessing Approval Workflows

  • Project Admins are the only individuals who have permission to create and edit approval workflows.
  • Within the Project Admin module, select Services and then Cost Management on the left side bar. Users are able to access the settings for the different components within Cost.
  • Navigate to the following tabs for:
    • Budget: Budget (Owner) Payment Application Approval Workflows
    • Cost: Contract Approval Workflows and Cost (Subcontractor) Payment Application Approval Workflows
    • Change Order: Owner Change Orders and Supplier Change Orders Approval Workflows
  • Note, the main tab and component names can be customized within General Settings.

2. Creating Approval Workflows

  • To create a Contract workflow, navigate to the Cost tab. To create Owner and Supplier Change Order workflows, navigate to the Change Order tab.
  • 1: Select “Create approval workflow”.
  • 2: In the dialog box, select an approval workflow template from the drop-down list. Templates are available for single-step or multi-step group reviews.
  • 3: Click “Next”.

  • 4: Define the workflow conditions.
    • For example, for Change Orders, choose either “Committed value” or “Type” and define remaining conditions.

  • 5: In the General Info section, name the workflow. When an item meets the defined conditions of a workflow, the workflow name will appear in the system as it progresses through the review process.
  • 6: In the Steps section, specify the details for each step in the workflow:
    • For each step, specify either single or multiple reviewers. Reviewers can be a user, role, or company. The reviewer must have Full Control or Admin permissions to the component (e.g. SCO tab) to participate in the review.
    • If multiple reviewers (a group approval step), specify whether every member of the group must review, or select the minimum number of reviewers required.
    • Note: When an approval workflow template is selected, the Reviewer Type field is filled in by default. For reviews with more than one step, this can be customized as required. For example, if a Three Step Approval template is selected, one of the single review steps should be changed to a group review step.
    • Specify the time allowed for each step.
    • Optionally, enter a name for each review and approval step. The step name will appear in the system as it reaches each review step.

 

  • 7: Click “Save”.

3. Reviewer Notifications and Submission for Signature

  • When an item satisfies the conditions of an approval workflow, a dialog box will appear, detailing the approval workflow it will be progressing through and enabling you to add a comment.
  • As an item progresses through each step in a workflow, the designated reviewer for that step will be alerted via email.
  • The reviewer can click “Open in cost management” to be directed to the item for review in the email. Respond appropriately and select submit.
  • The final reviewer submits the item to the external party for their approval and signature.
  • If using the SignNow integration for e-signature, documents will be sent to signers defined in the signature template.
  • The workflow bar in the details flyout panel displays the item’s status, ball-in-court, and expected due date as it moves through the workflow.
  • Activity is captured in the item’s activity log.

4. Edit and Manage Approval Workflows

  • To edit/manage a specific workflow, next to the workflow select the “More” menu and choose from the following options:

 

    • Configure: to edit the workflow settings
    • Duplicate: to make a copy of the workflow. Tip: This is useful when creating a new workflow using settings similar to an existing one. Configure the copied workflow to give it a unique name, and change other settings as required.
    • Deactivate: to deactivate the workflow so it won’t be used
    • Move Up: to move the position of the workflow up in the list
    • Move Down: to move the position of the workflow down in the list
    • Delete: to permanently delete the workflow

Budget and Contract Management

BIM 360 Cost Management enables teams to minimize risk by managing all cost-related construction activities in a single software. It provides a real-time summary view of all budget items and contracts, giving a clear picture of revenue, costs, forecast and variance related to each item.

1. Budget Tab Overview

  • Open the module picker and select Cost Management. Select the Budget tab. The budget tab displays a real-time view of the project’s financial health. Note, tab names can be customized by the Project Admin within settings.
  • All cost activities are automatically pulled into the overall budget summary, providing clear visibility into cost impacts and making necessary forecast adjustments.

  • To avoid accidental changes, the budget can be locked. If it’s not yet locked, select “Lock budget”. Only Project Admins can edit the original budget after it is locked.
  • For a comprehensive view of a budget item, select the item to open the details flyout panel. Information such as associated contracts, budget transfer history, forecast adjustments, etc. is available.

  • Locations can be added to budget items within the Details section of the flyout panel. By doing this you can filter and group to see how much money is allocated to specific areas in the building. Note, Project Admins configure locations within the Project Admin module > Services > Cost Management > Locations.

  • 1: Select the Export button to export formatted budget reports. The Excel report provides the option to include additional historical data. With the PDF report, choose to export a full report with all columns except Custom Attributes or an budget report with columns in General and Budget.
  • 2: Select the filter icon to filter/group the budget summary view based on multiple conditions.
  • 3: To save a filter and switch between saved views, select the “Default view” button.

  • 4: Select the Control icon to control the visibility and order of columns within the table. Select the column headers to sort in ascending or descending order.
  • 5: Select the chart icon to view budget and cost trend charts.
  • 6: Select the Plan icon to open a set of capabilities that allows users to plan schedule-related allowances such as General Conditions in a Gantt type view. More details are in the Method-Related Planning chapter.
  • 7: Select the edit icon to enable edit mode. If the user has “view only” permission, they can’t make edits.

2. Budget Edit Mode

Users with “full control” permission for the Budget component can edit the budget. If the budget is locked, only Project Admins can make edits. Once the original budget is locked, it cannot be undone. With the budget in edit mode:

  • 1: Select “Add” to manually enter new budget items.
  • 2: Select “Download template” to download a budget import template.
  • 3: Select “Import” to import an Excel file.
  • 4: Select the “Export” button to export the formatted budget Excel report.
  • 5: Select the filter icon to filter/group the budget summary view based on multiple conditions.
  • 6: To save a filter and switch between saved views, select the “Default view” button.

  • 7: Select the Control icon to control the visibility and order of columns within the table. Select the column headers to sort in ascending or descending order.
  • 8: Within each budget item, select the pencil icon to edit the budget name.
  • 9: Click within the Quantity, Unit, and Unit Cost columns to edit the information.

  • 10: Select the checkbox next to a budget item or the three-dot menu to access additional actions for that specific budget item; for example, make a Change Order Transfer or delete the item.

  • 11: Create a Main Contract SOV or Contract by selecting one or more items. The ability to compile them into one contract is also available.

 

    • There is no restriction on hierarchy levels, and the totals from all child items are rolled up to the parent and divided by the parent quantity to provide a unit cost, allowing visibility into how the budget number was derived.

3. Contract Tab Overview

  • Open the module picker and select Cost Management. Select the Cost tab. This is where supplier contracts are managed. Note, Tab names can be customized by the Project Admin within settings.
  • The Contract view is similar to the Budget view.

  • Select the Export button to export formatted contract summary reports.
  • Select the filter icon to filter/group the contract view based on multiple conditions.
  • To save a filter and switch between saved views, select the “Default view” button.

  • Select the Control icon to control the visibility and order of columns within the table. Select the column headers to sort in ascending or descending order.
  • Select the chart icon to view budget and cost trend charts.
  • Select the edit icon to enable edit mode. If the user has “view only” permission, they can’t make edits.

  • Select the contract name to open the details flyout panel. The details flyout panel provides more information such as Supplier details, scope of work, schedule of values, documents, billing periods, etc.

4. Contract Edit Mode

Users with “full control” permissions for the Contract component can edit, in edit mode:

 

  • 1: Select “Add” to manually enter a contract item.
  • 2 & 3: Select “Import” to open the Contract Import window to import an Excel file. In the Contract Import window Select “Download template” to download a contract import template.
  • 4: Select the “Export” button to export formatted contract summary report.
  • 5: Select the filter icon to filter/group the contract view based on multiple conditions.

  • 6: To save a filter and switch between saved views, select the “Default view” button.
  • 7: Select the Control icon to control the visibility and order of columns within the table. Select the column headers to sort in ascending or descending order.

  • 8: Within individual contract items, select the pencil icon to edit the contract name.
  • 9: Click within the Type and Budget Code columns to edit the information. Project Admins create the list of contract types within the Cost settings in Settings within the Project Admin module.
  • 10: Select the checkbox next to a contract or the three-dot menu to delete it.

  • To edit additional information pertaining to a specific contract, select the contract name to open the details flyout panel. Key items:
    • Budget Code – Provides a list of all unallocated budget items. Create the connection between contract and budget item by assigning from this list.
    • SOV (Schedule of Values) – By default, the SOV will inherit any budget item build-ups from the connected budget item. They can be removed by right-clicking if the user wants to create a different list of items. They can also be appended or edited and the values overwritten to create the correct award value for the contract.

    • Documents – Automatically generate the contract, package the contract with associated documents, and email from the system.
    • Billing Periods – Create and manage billing periods for payment applications.
    • Custom Attributes – Project Admins can customize the type of information that needs to be captured for contracts. Steps for creating a Custom Attribute can be found in the Custom Attributes chapter.

5. Copy Supplier SOV Subitems to Main Contract

Some Owners require that their payment applications reflect the exact schedule of value breakdown the General Contractor gets from their subcontractors. However, the General Contractor may not have some of their subcontractor SOV’s established until later. Follow the below steps to learn how to copy supplier contract SOV subitems to the main contract so the Owner’s payment applications include the required information.

 

  • Open the Suppliers contract within the Contract tab in the Cost tool. Next, scroll to the Schedule of Values section in the flyout panel and select the three-dot menu. There you can manually add subitems or import an Excel list. Note, subitem amounts must equal the exiting SOV amount.

  • Next step, go to the Main Contract tab within the Budget tool and expand all. Navigate to the contract and open the contract’s flyout panel. Select the three-dot menu to copy subitems to Main Contract.
  • The new SOV subitems will now display the next Owner payment application.

6. Expand Supplier SOV to Full Page

  • When the Contract SOV root nodes exceed hundreds of items, having the full-screen view makes it easier to visualize the data.
  • There are two ways to expand the SOV section of a specific Contract to full-screen. 
    1. Hover over the contract row and select the expand icon. 
    2. Open the contact flyout and select the “View Schedule of Values in full page” button within the Schedule of Values section. 
  • Once in full page view, select the filter icon to group by budget code segment. Also, custom views can be saved for later for quick referencing within this view. 

 

Fundamental Forecasting

With all cost activities automatically pulled into the overall budget summary, teams have clear visibility into cost impacts, with a few clicks users can easily make necessary forecast adjustments.

1. Making Forecast Adjustments

  • Within the Budget tab in Budget, the following columns are available to make and manage forecast adjustments.
    • Actual Costs
    • Forecast Adjustments
    • Forecast to Complete
    • Forecast Final Cost
    • Forecast Variance

  • When a forecast adjustment needs to be made/edited, select the three-dots next to the Budget item then select Forecast Adjustment.
  • In the Edit Forecast Adjustment dialog box select “add line item” and fill in the necessary information. Multiple items can be added. To delete an item, select the three dots then Delete.

  • The total adjustments will appear in the Forecast Adjustments and Forecast Variance column. The Forecast Cost to Complete and Forecast Final Cost will now reflect the change.

Cash Flow Forecasting

Access a project-level cash flow analysis and quickly visualize the difference between planned actual and forecast with built-in dynamic charts to ensure plans are being met, risk is mitigated, and profit is maximized.

Setting Preferred Forecast Period

  • Within Settings Admins can set preferred forecast periods; weekly or monthly. Once a forecast distribution is created on any budget item this setting cannot be changed.

Built-In Forecast Distribution Curves

  • Perform forecast distributions for each budget line item with four built-in forecast distribution curves, including front-loaded, rear-loaded, typical, and linear (when required, you can manually override).
  • There are three ways to access the distribution curve functionality.

 

    • OPTION 1: Via the Forecast Distribution section of the budget item’s details flyout panel.

Option 1

    • OPTION 2: Within the Forecast Tool via the more menu (three-dot menu) of a budget line item in the Cost & Time view.
      • From this view you can also select multiple budge items and batch create forecast distributions.
      • If you use a grouped view (via. filters) you can multi-select by the group header.

Option 2

    • OPTION 3: Within the Forecast Tool via the more menu (three-dot menu) of a budget line item in the table in the Cashflow view.

Option 3

  • A Create Forecast Distribution dialog box will appear when creating a forecast distribution, add in the distribution start and end date. When performing distributions to items connected to the schedule, dates automatically pull in. 
  • Choose the Curve from the drop-down menu; front-loaded, rear-loaded, typical, and linear. Note, a Budget with a time-based unit can only be distributed with a linear curve.
  • Select, Create. 

  • The details flyout panel will update to display a graphic representation of the distribution
  • Choose to display the information by amount or percent. 
  • Select the three dot more menu to delete the distribution.
  • Use the control icon to access the chart’s settings to display the chart by period, cumulative, or cumulative & by period. 
  • Select the arrow icon to expand the chart view. 

  • Note: Work Completed and Actual Cost is automatically added into the distribution if Revised Budget and Forecast Final Cost has not been distributed.
    • This information comes from this forecast distribution date.
    • By default, it comes from the date the item was approved, but you can edit it.

  • Hover over a specific point on the chart to view detailed information. 

  • In the table, scroll to view the distribution periods.
  • As projections are made, the system will auto-flag if the distribution total doesn’t match the forecast-final cost and direct you to open the distribution details.

  • The distribution details will open in the Cash Flow tab.
  • There you can manually make the distribution.

  • To customize the distribution further, select the more menu to add periods or delete the last period.

Project Level Cash Flow Analysis

  • Once all budget line items are forecasted, teams can access a project-level cash flow analysis to easily visualize the cash flow distribution throughout the project lifecycle.
  • This real-time summary enables teams to see planned actual and forecast quickly. It also provides the ability to drill into details if needed.
  • To access this, open the Forecast tool via the left sidebar then, select the Cashflow tab.

Time-Versus-Money Chart Navigation

 

  • To display the built-in dynamic time-versus-money chart, select the chart icon.
  • Click Revised Budget, Work Completed, Actual Cost, or Forecast Final Cost to switch between views. 
  • Choose to display the information by amount or percent. 
  • Use the control icon to access the chart’s settings to display the chart by period, cumulative, or cumulative & by period. 
  • Hover over a specific point on the chart to view detailed information. 

Table Navigation

 

  • Use the control icon to rearrange columns and hide/show months. 
  • Use the filter icon above the cart to filter/group the information within the table. 
  • To save views, select Default View, then Save Current Views. 

  • To dive deeper, hover to the right of the line item’s name to access the option to open details view. 

  • With the details view open, select the name of a budget item to view specific information/make updates within the details flyout panel. The graph will also change to display the information relevant to that item for the particular view you’re in. 
  • To delete distribution directly from the table select the three dot more menu.

Forecast Distribution Date in Details Flyout Panel

  • When a budget payment application, cost payment application or expense is approved, the ‘Forecast Distribution’ date field within the details flyout panel will display the same date as the ‘Approved’ date.
  • However, it can manually be modified manually to meet your needs.

Change Order Management

A typical construction project can have dozens of Change Orders. Improve tracking of Change Orders across the entire approval process, and view details of Cost Item impacts as well as historical reference points with Cost’s Change Order capabilities.

1. Potential Change Order Tab

 PCO’s (Potential Change Orders) are the starting point of any budget or cost change. Cost items are added providing a connection back to the affected budget, contract and supplier. Cost items can be created directly in the cost item view and assigned to a PCO later but the typical workflow is as follows: 

  • 1: Select “Add” to create a new PCO.
  • 2: Select Scope, In (Cost Change Only) Out (Additional Budget and Cost Change) or Contingency (Budget and Cost Change) If a change is Budget side only simply do not add any values to Estimated, Proposed or Committed columns.
  • 3: Type is an optional field if you’d like to be able to number, track or group change orders by their type.
  • 4: Source Type and Source Ref are also optional if you’d like to track or group based on the origin of the change.
  • 5: “Export” allows you to export a PDF or CSV PCO report.

PRO TIP: If you see your calculated markups are out of sync select the line item and in the “Apply Markup” drop-down select the necessary markup from the list.

  • 6: Column settings allows you to select the columns you wish to include in your view.
  • 7: View selector allows you to store and recall your preferred grouping/column visibility.
  • 8: Select the PCO name to open the details flyout panel, the pencil allows you to edit the name.
  • 9: Select the three dot icon or right click to access the context menu to add cost items, change status, etc Reference the last section in this chapter for more information on cost items.
  • Leaving a PCO as draft will mean any costs are not shown or used in calculations in the budget/contract overview. Setting status to Open triggers those calculations and impact will be shown in the overview

PRO TIP: Source Types are created/managed by the Project Admin within the Change Order settings in Settings.

  • Depending on the budget and cost statuses when a PCO is selected, the below options will appear.
    • Set to open
    • Ability to generate an RFQ, RCO, OCO, or SCO
    • Ability to delete it

PRO TIP: To detach a cost item from a PCO expand the row and select the item, a detach button will appear.

  • To add a location to a PCO use the Location field within the table. By doing this you can filter and group to see a location-based view of changes. Note, Project Admins configure locations within the Project Admin module > Services > Cost Management > Locations.

2. Generating a Request for Quotation from a Potential Change Order

Request for Quotation (RFQ) is the document generated to solicit pricing from a supplier.

  • A single RFQ that includes all the associated Cost Items can be generated or individual RFQs for specific Cost Items within the PCO can be generated.

  • There are three different ways to generate an RFQ:
    • Option 1: Select the checkbox next to the PCO or specific Cost Item. A “Generate” drop-down menu will appear. Choose “RFQ”.
    • Option 2: Select the three-dot menu next to the PCO or specific Cost Item and scroll to “Generate”. Then choose “RFQ”.
    • Option 3: Select the PCO name to open the details flyout panel, then choose “RFQ” from the “Generate” drop-down menu. This option is available only for generating a single RFQ that includes all associated Cost Items.
  • Once an RFQ has been generated, the item moves to the RFQ tab.

3. Request for Quotation Tab

The Request for Quotation (RFQ) tab is within the Change Order tab in Cost Management. Note, tab names can be customized by the Project Admin within settings.

    • 1: The items status auto updates to “Draft” after a RFQ is generated from a PCO.

    • 2: Select the Control icon to edit position and visibility of columns within the table.
    • 3: The Response Due column will be populated when a date is added in the dates section of the details flyout panel.
    • 4: To delete an item, update the item’s status, generate/regenerate a document. Then, select the checkbox next to the line item or the three-dot menu.

  • To “detach” a Cost Item from an RFQ, expand the row and select the three dots or check the box. The detach button will appear. It will still be part of the PCO.
  • Click into the Estimated and Proposed columns to add necessary information.

  • Select the item’s name to open the details flyout panel. Editing the RFQ can be done within the flyout panel.
  • In the details flyout panel, selectable workflow-based actions (buttons) will appear to guide the user through the process.
    • For example, when the RFQ status is “Open,” a “Request Quotation” button is visible. Note, a Supplier needs to be listed in the Supplier Details section.
    • Once the RFQ is sent, the next options appear: “Set as Proposed” or “Rejected”, and so on.
    • When Accepted, select “SCO” to generate a Supplier Change Order.

  • To generate the RFQ documentation, scroll to the documents section of the details flyout panel and select “Add document”. Choose “Generate from document template” and pick the appropriate template. This process utilizes the document templates created in Settings.
  • Once the document is generated, select the three-dot menu to view additional options. To email the document(s) directly from the system, choose the three-dot menu next to Document Package, and select “Send by email”.

4. Generating a Request for Change Order from a Potential Change Order

Request for Change Order (RCOs) are upstream budget change orders. They are a means of requesting a change in the contract between the Owner and the Main Contractor. Typically, the RCO created by the Main Contractor is built from one or more Cost Items and sent to the Owner.

 

  • There are three different ways to generate an RCO.
    • Option 1: Select the checkbox next to the PCO. A Generate drop-down menu will appear. Choose RCO.
    • Option 2: Select the three-dot menu next to the PCO, and scroll to Generate. Then choose RCO.
    • Option 3: Select the PCO name to open the details flyout panel, and then choose RCO from the Generate drop-down menu.
  • Multiple PCOs can be rolled up into a single RCO. Select the checkbox next to the PCOs to generate into a single RCO. The process is the same as generating a single document. However, the RCO will be a combination of the selected PCOs. The Cost Items will be combined, and the scope is auto-populated but can be adjusted.
  • Once an RCO has been generated, the item moves to the RCO tab.

PRO TIP: The PCO must have a Budget Status of “Open” and a “Submitted” value to be able to generate an RCO

5. Request for Change Order Tab

The Request for Change Order (RCO) tab is within the Change Order tab in Cost Management. Note, tab names can be customized by the Project Admin within settings.

 

  • 1: The item’s status auto-updates to “Draft” after an RCO is generated from a PCO.
  • 2: To delete an RCO and update the status select the checkbox next to the line item. Select the three-dot menu for additional options.
  • 3: Select the Control icon to edit position and visibility of columns within the table.
  • 4: Select the items name to open the details flyout panel. Editing the RCO can be done within the flyout panel.

  • In the details flyout panel, selectable workflow-based actions (buttons) will appear to guide the user through the process.
    • For example, when the RCO status is “Submitted,” “Set as Accepted” and “Set as Rejected” buttons are visible.
    • By selecting “Set as Accepted”, the status color changes, and the next options are “Set as Rejected,” “Generate”, and “Revert to Submitted”.
    • With the status as “Accepted”, an OCO or an SCO can be generated.

  • To generate RCO documentation, scroll to the documents section in the details flyout panel and select “Add document”.
  • Choose “Generate from document template” and pick the appropriate template. This process utilizes the document templates created in Settings.
  • Once the document is generated, select the three-dot menu to view additional options. To email the document(s) directly from the system, choose the three-dot menu next to Document Package and select “Send by email”.

6. Generating an Owner Change Order from a Request for Change Order

Owner Change Order (OCO) represents a Change Order from the Owner to the Main Contractor/Construction Manager. These documents are built from one or many change requests (RCOs) by processing the RCOs into an OCO. The signed OCO legally amends a contract to effect a change in requirements, cost, or schedule to the previously negotiated contract.

  • The RCO status must be “Accepted” to generate an OCO.

  • There are three different ways to generate an OCO.
    • Option 1: Select the checkbox next to the RCO. A Generate drop-down menu will appear. Choose OCO.
    • Option 2: Select the three-dot menu next to the RCO, and scroll to Generate. Then choose OCO.
    • Option 3: Select the RCO’s name to open the details flyout panel. Then choose OCO from the Generate drop-down menu.
  • Multiple RCOs can be rolled up into a single OCO. Select the checkbox next to multiple RCOs to generate a single OCO.
  • The OCO will be a combination of the selected RCOs. The Cost Items will be combined and the scope is auto-populated but can be adjusted.
  • Once the OCO has been created, the item moves to the OCO tab.

7. Owner Change Order Tab

The Owner Change Order (OCO) tab is within the Change Order tab in Cost Management. Note, tab names can be customized by the Project Admin within Settings.

 

  • 1: The items status auto updates to “Draft” after an OCO is generated from an RCO.
  • 2: To delete an item or update the item’s status select the checkbox next to the line item. For additional options select the three-dots.
  • 3: Select the Control icon to edit position and visibility of columns within the table.
  • 4: Select the item’s name to open the details flyout panel. Editing the OCO can be done within the flyout panel.

  • In the details flyout panel, selectable workflow-based actions (buttons) will appear to guide the user through the process.
    • For example, when the OCO status is “Open”, a “Set as Submitted” button is visible. By selecting it, the status color changes and the next options are “Set as Approved” or “Set as Rejected”.
    • Once the status is “Approved”, an SCO can be generated. It can be generated now or select “Set as Executed” and then generate it.

  • To generate the OCO documentation, scroll to documents and select “Add document”. Choose “Generate from document template” and pick the appropriate template. This process utilizes the document templates created in settings.
  • Once the document is generated, select the three-dot menu to view additional options. To email the document(s) directly from the system, choose the three-dot menu next to Document Package and select “Send by email”.

8. Generating a Supplier Change Order

Supplier Change Order (SCO) is a downstream cost Change Order which amends the original Supplier’s contract.

 

  • There are a few different ways you can generate an SCO within Cost:
    • From a PCO with a budget status of “Open”, “Approved”, or “Executed”, and cost status of “Open” or “Proposed”.
    • From an RFQ with a status of “Proposed”.
    • From an RCO with the status of “Accepted”.
    • From an OCO with the status of “Approved” or “Executed”.

 

  • To generate a single SCO consisting of all Cost Items associated with a “parent” line item, select the checkbox next to the parent.
  • To create individual SCOs for specific Cost Items within a “Parent”, select the box next to the Cost Item.
  • You can also select multiple SCOs with multiple “parents” to generate a single SCO.

9. Supplier Change Order Tab

The Supplier Change Order (SCO) tab is within the Change Order tab in Cost Management. Note, tab names can be customized by the Project Admin within Settings.

  • 1: The items status auto updates to “Draft” after an SCO is generated.
  • 2: To delete an item or update the item’s status select the checkbox next to the line item. For additional options select the three-dots.
  • 3: Select the Control icon to edit position and visibility of columns within the table.
  • 4: Select the item’s name to open the details flyout panel. Editing the SCO can be done within the flyout panel.

  • In the details flyout panel, selectable workflow-based actions (buttons) will appear to guide the user through the process.
    • For example, when the SCO status is “Open”, a “Send” button will be visible. By selecting it, the status changes and the next option is “Set as executed”.

  • To generate the SCO documentation, scroll to documents and select “Add document”. Choose “Generate from document template” and pick the appropriate template. This process utilizes the document templates created in settings.
  • Once the document is generated, select the three-dot menu to view additional options. To email the document(s) directly from the system, choose the three-dot menu next to Document Package and select “Send by email”.

10. RFI to Potential Change Order

Project Management Admins and RFI Managers with full control permission level for the Cost Item and PCO component can create a Potential Change Order (PCO) from an RFI or link existing RFIs to PCOs. This process creates a bi-directional link between the two records.

Creating a new PCO from an RFI:

  • In the Project Management module, in the RFI tab, in both a new RFI or existing RFI, scroll to references and select “Add reference”, then “PCO”.
  • In the Add PCO reference dialog box, select “Create”.
  • Fill in the PCO name and description, then select “Create”.
  • This information will copy over from the RFI to the PCO. It can be altered directly in the PCO record later.

Linking RFIs to PCOs:

  • To link RFIs to PCOs, follow the same steps as above. However, when the “Add PCO” reference dialog box appears, simply select the PCO(s) from the list and click “Add PCO”.
  • To unlink a PCO from an RFI, hover over it and select the “X”.

Accessing Linked RFIs and PCOs from the list views:

  • Only Admins and RFI Managers can view linked PCOs. Within the RFI list view in the linked references column, select the PCO number to open the PCO in Cost.
  • In Cost Management within the PCO details flyout panel, select the RFI to be directed to the RFI in the Project Management module.

11. Cost Item

Cost Items are the individual detailed items for each budget code associated with a potential change. The typical workflow is to create a Potential Change Order (PCO) and add Cost Items to it. However, in the Cost Item tab, easily add Cost Items or edit existing Cost Items.

This works similarly to the edit mode in the Contract tab.

  • Open the product picker and select Cost.
  • Select the Change Order tab, then the Cost Item tab.

PRO TIP: Project Admins can customize the main menu name (Change Order) and the subtab names (Cost Item, PCO, RFQ, RCO, OCO, SCO) and change the order of the tabs within Settings. Refer to the Settings and Permission chapter for more details.

 

  • 1: To manually enter a Cost Item, click “Add”.
  • 2: To export a PDF or Excel Cost Item report, click “Export”.
  • 3: The Control icon opens the column settings.

  • 4: Budget Status displays the current status of the cost item in the budget request workflow.
  • 5: Select the link to open the “container” for whichever part of the process the Cost Item is in.

  • 6: Select the pencil icon to edit the Cost Item name
  • 7: Select the three dots to delete a Cost Item.
  • 8: Select the name of a Cost Item to open the details flyout panel.

Details flyout panel

 

  • Edit the Cost Item’s details within the details flyout panel. To access the details flyout panel, select the Cost Item’s name.
  • In the details flyout panel under Cost Summary, the Cost Item can be broken down into a more granular level of detail by selecting “Define hierarchy”.

  • A location can be added to a Cost Item using the Location field within the table or within the Details section in the flayout panel. You can then filter and group to see a location-based view of cost items. Note, Project Admins configure locations within the Project Admin module > Services > Cost Management > Locations.

Assigning Cost Items to a Potential Change Order

 

  • Existing or new Cost Items created directly in the Cost Item tab can be “assigned” to a Potential Change Order (PCO) by:
    • selecting the checkbox next to the Cost Item. Once selected, an “Assign” button appears. Click the drop-down to assign.
    • or the three-dot menu next to the item’s name, hover over Assign.
  • An assign window will pop up. Type in search criteria to filter the list. Select the PCO to add the Cost Item.

Expense Management

BIM 360 Cost Management includes a robust set of functionality that enables teams to streamline the management of expenses. Not only does it streamline invoice reviews and approvals, but teams can utilize up-to-date actual cost data for more accurate forecasting and add expense data to Budget Payment Applications.

1. Expenses Tab

  • Open the module picker and select Cost Management.
  • Select the Cost tab, then the Expense tab. This is where users can manage all invoices and expenses outside of pay applications.
  • To add an expense, you must have full control permission for this tab. Project Admins control the permission levels within the project admin module.
  • There are three ways to add expenses:
    1. Add from an existing contract
    2. Manually
    3. Use APIs to build an integration between Cost and the user’s accounting/ERP system to automatically flow data between the two platforms.

2. Adding Expenses from an Existing Contract

In the Cost tab, select the Expense tab

  1. Select the “Add from contract” button.
  2. In the dialog box use the drop-down to find the correct contract.
  3. Select “Add.”

  • Details are automatically brought in. For example, Name, Supplier, Contract, and Amount. The item is also automatically connected to the correct budget code to show liability.

    • Scope: In the Scope column, use the drop-down menu to categorize the payment type, Full or Partial.
    • Type: In the Type column, click to access the drop-down and select the appropriate expense type (e.g., Internal, Invoice, Overhead Cost).
      • Project Admins create the list of types in Settings. Refer to Settings and Permissions to learn how this is done.

    • Amount Paid: Click in the Amount Paid field to add the amount.
    • Date Issued: In the Date Issued column, use the calendar to select the appropriate date. For example, the date the invoice was issued.
    • Reference Number: To include a reference number, click into the Reference Number field.
    • Status: In the Status column, use the drop-down menu to set the appropriate status.
    • Date Paid: When the items status is set to paid, the date will automatically populate in the Date Paid field.

 

  • If Cost is connected to your Accounting/ERP system as changes are made the information will automatically update in both systems.

 

PRO TIP: To delete a subitem or expense, select the three dots in the appropriate row. To delete an expense or subitem, the expense status must be Draft, Pending, Revise and Resubmit, or Rejected.

3. Manually Adding Expenses

If there is no purchase order, expenses can be manually added to track it and show liability against the budget.

  • In Cost, select the Expense tab.
    • 1: Select the arrow next to the “Add from contract” button, then select “Add.”

    • 2: Expense Name: In the Name column, type in the name for the expense.

    • 3: Supplier: In the Supplier column, use the drop-down menu to choose the appropriate Supplier. If it’s not listed, type it in the search box and choose enter to add it.
    • 4: Type: In the Type column, use the drop-down to select the appropriate expense type.
    • 5: Date Issued: In the Date Issued column, use the calendar to select the appropriate date.

    • 6: Add Subitem: To add cost details, select the three dots to the right of the Expense name. You can add an unlimited number of subitems to a contract as long as the status is Draft.

    • 7: Item Name: In the Name column, click to manually add the name of the item, then push enter.
    • 8: Budget Code: In the Budget Code column, use the drop-down menu to select a budget item. You can type to filter the list and use the group by segment to organize the list as preferred.
      • If the budget code isn’t listed, choose “Create” it. If creating the code manually, click the field to save it.

PRO TIP: The option to group by budget code segment is also available.

    • 9: Amount: In the Amount column, click to manually add the amount.
    • 10: Scope: In the Scope column, use the drop-down menu to categorize the payment type, Full or Partial. This will automatically update the contracts scope.

    • 11: Status: In the Status column, use the drop-down menu to set the appropriate status.
    • 12: Date Paid: When the items status is set to paid, the date will automatically populate into the Date Paid field.

To delete a subitem or expense, select the three dots in the appropriate row. To delete an expense or subitem, the expense status must be Draft, Pending, Revise and Resubmit, or Rejected.

4. Adding Expenses to Budget and Payment Applications

Associating expenses to a budget payment application is a similar process to associating Cost Payment Applications to the budget payment application.

  • In Budget, navigate to the Budget Payment Application tab.
    • 1: Use the drop-down menu to navigate to the correct contract.

    • 2: Select the contract name to open the details flyout panel.
    • 3: Scroll to the Associate Expense section and select “Add existing.”

    • 4: A list of approved expenses will populate, select the one(s) you wish to associate.

    • 5: The associated expense will appear in the details flyout panel.

PRO TIP: When generating the Budget Payment Application document, the option is given to collate associated expenses, attachments, and Supplier pay applications together for submission to the Owner.

5. Viewing Expense Details in the Budget Summary

Similar to approved Cost Payment Application details pulling into the budget summary, approved/paid expenses automatically pull into the budget summary view, giving users the ability to view actual cost breakdowns and make accurate forecast adjustments.

  • In Budget, navigate to the Budget tab.
  • Scroll to the right to the Actual Cost column. Expenses with an approved or paid status will display in the list.

  • Select the total in the Actual Cost column to view the cost breakdown.
  • Select the Budget Name to open the details flyout panel for more detailed information.

  • For any budget item, if a forecast adjustment, budget transfer, or Change Order transfer needs to be made, select the three-dot menu next to the budget item name.

Payment Applications

Avoid risks and errors resulting from the use of disconnected cost management tools, and benefit from real-time visibility into how payments are affecting the project budget to maintain a real-time view of the financial health of the project.

1. Creating Main/Prime Contracts

Open the module picker and select Cost Management. Select the Budget tab, then the Main Contracts tab. To create a contract, users must have full control permission for this tab. Project Admins control the permission levels within the Project Admin module.

  • 1: Select the edit icon.
  • 2: In edit mode, an “Add” button will appear; select it to create a new main contract(s).
  • 3: Type the contract code, name, and select the type drop-down.
  • 4: Select the columns you wish to include in the summary view by clicking the gear icon.
  • 5: To export the information in the summary view to Excel, select the “Export” button.
  • More than one contract can be created. If, more than one contract is created select the three-dot menu after the contract name to set which is default. The three-dot menu also provides addition options (e.g., ability to add sub-items or delete the contract).

PRO TIP: To edit a contract after it is created, enter edit mode.

2. Creating the Main/Prime Contract Schedule of Values (SOV)

SOVs can be manually entered or automatically created from selected items within the Budget tab.

Manually creating the SOV:

 

  • In the Main Contract tab, select the edit icon.
  • Next to the desired main contract, select the three-dot menu, then “Add subitem.” Note: Once a payment application exists, the contract will be locked, and edits can’t be made.
  • A new line will appear under the main contract. Fill in the necessary information. Either type in a value or associate it to a budget code by selecting within the budget code column; the value will auto-populate.

Automatically creating the SOV:

  • 1: Within the Budget tab, select the Budget tab and then the edit icon.
  • 2: Select the budget items to associate with the contract.
  • 3: A “Create Main Contract SOV” button will appear. Select it.

  • 4: Within the “Create Main Contract SOV” dialog box, select the contract from the list.
  • 5: Select what to create the SOV from; when done, click “Create”.

  • The Main Contract SOV will now be created automatically and link to the budget. This connection allows users to see what they will be paid and what they need to pay their Suppliers.

3. Creating Billing Periods/Master Schedule

Billing periods can be set up from the main contract’s details flyout panel or within the Budget Payment Application tab.

From Main Contract details flyout panel:

 

  • Select the main contract to open the details flyout panel. Within the panel, scroll to the Master Schedule section and select the “Manage” button.
  • In the “Manage master schedule” dialog box, either copy billing periods from another main contract using the drop-down menu or manually create new periods.
  • Once the billing periods are created, manage them easily within the details flyout panel under the “Master schedule” section. In this view, easily see payment application statuses and amounts for each period.

From Budget Payment application tab:

 

  • In the Budget Payment application tab, choose the desired contract.
  • Select the “Set up master schedule” button.
  • The “Manage master schedule” dialog box will open, follow the same steps as above.

4. Managing Cost Payment Applications

Supplier payment applications can be managed from the Budget Payment Application tab within the Budget tab. They can also be managed in the Cost Payment Application tab within the Cost tab.

From Budget Payment application tab:

 

  • 1: Use the drop-down menu to select the desired main contract.
  • 2: Use the drop-down menu to choose the correct billing period or use the arrows to navigate between periods.
  • 3: Select “View associated costs”. This will open the details flyout panel.
  • 4: In the Associated Cost Payment Application section, select “Create” to create a new cost payment application. To connect an existing application to the contract select “Add existing”.
  • 5: Once created/selected, the cost payment application(s) will appear. To update a Cost Payment Application’s information, select the billing period. This will take you directly to the Cost Payment Application.

From Cost Payment Application tab:

In the Cost tab, select the Cost Payment Application tab.

  • 1: Select the arrow next to “Batch create”, then “Create”.
  • 2: Use the drop-down menu to select the appropriate contract.
  • 3: Select “Set up billing periods” and choose the appropriate option. If creating from scratch, follow the same steps covered in section 3, “Creating billing periods/master schedule”.
  • 4: Choose the correct billing period or use the arrows to navigate between periods.
  • 5: To batch create cost payment applications, select “Batch create”.
  • Note: the export button allows you to export an open payment application to Excel. The Excel file can then be filled out by the supplier and imported back into Cost Management where the information will be automatically populated.

Updating Cost Payment Application information:

  • In the Cost tab, select the Cost Payment Application tab.
  • Then, hover over a line item and select the icon. Or select the three-dot menu to open details view.

  • 1: Scroll to to the right and stop at This Period, click within the table to make necessary updates. The system will automatically update to reflect the changes.
  • 2: Approved Supplier Change Orders (SCOs) will automatically be added based on the approved date. If one is not visible, select “Add change orders” to manually insert it.
  • 3: Users that would like to have supplier input for their claimed work amount can turn on a new column group.

  • 4: To request input from the Supplier, select the “Request Input” button. Note, the Supplier will need access and the correct permission level.

  • The three-dot menu next to “Request input” provides the following options:
    • Ability to export the payment application. This is useful if someone does not have access to the system. They can populate data into the yellow highlighted area; then you can import the information back into the system.
    • Ability to import data.
    • Ability to delete the payment application.

Cost payment details flyout panel:

 

  • To open the details flyout panel, click the payment application’s name within the table.
  • Expand and collapse the different sections.
  • Within details, the status can be updated.
  • View a concise payment application summary table.
  • View a change order summary.
  • Quickly generate or access generated documents.
  • If the cost payment application is associated with a budget payment application, details will be displayed. Select the billing period to open the budget payment application.

PRO TIP: If custom attributes have been created, they will appear. For more information about custom attributes, refer to the Custom Attributes chapter.

5. Managing Budget Payment Applications

Owner pay applications can be managed from the Budget Payment Application tab within the Budget tab.

Budget payment application tab:

 

  • 1: Use the drop-down menu to select the appropriate contract.
  • 2: Use the drop-down menu to choose the correct billing period, or use the arrows to navigate between periods.
  • 3: Select the columns to include in the table by clicking the gear icon.
  • 4: Approved owner change orders automatically pull in.  

  • 5: To manually insert a change order, select “Add change orders” and use the drop-down to select the change order. 
  • The three-dot menu next to “Submit” provides the following options:
    • Ability to export the payment application.
    • Ability to unhide subitems.
    • Ability to show change orders as a column.
    • Ability to delete the payment application.
    • Ability to allow overbilling.
  • To submit, click the “Submit” button.

Budget payment application details flyout panel:

  • To open the details flyout panel, click the payment application’s name within the table.
  • Expand and collapse the different sections.
  • Within details, the status can be updated.
  • View a concise payment application summary table.
  • View a summary of the change orders.
  • Quickly generate or access generated documents.
  • Create or add existing cost payment applications. Cost payment applications can be aggregated by Amount or Percent.
  • Ability to associate expenses by selecting “Add existing”. Expenses can be aggregated by Amount (Work Completed), Quantity, and Amount (Materials on Site).
  • Select the update button to update values in work completed this period from associated cost payment applications and expenses. Note, Associated Expense must have a status of “Approved” in order to update.

PRO TIP: If custom attributes have been created, they will appear. For more information about custom attributes, refer to the Custom Attributes chapter.

6. Associated Costs Report Export

  • Easily export an associated costs back-up report of all cost payment application details and expenses from the flyout panel to support the budget payment application.
  • Open the flyout panel and scroll to the Associated Costs section.
  • Select the Export drop-down to choose a PDF or Excel report.

7. Document Generation

Create standard documentation formats that automatically populate directly from the system. See the Document Templates chapter of this guide for details on how to access the document templates and create your own.

 

For example, automatically generate a payment document which provides the information required to populate documents such as the AIA G702-1992 and AIA G703-1992 forms.

Generating Documents:

 

  • 1: Within the Main Contract, Cost or Budget Payment Application details flyout panel, scroll to the Documents section, select “Add document” and choose “Generate from document templates”.
  • 2: Select the desired template from the drop-down list and click “Generate”. The document templates are controlled by the Project Admin. Refer to the Document Templates chapter for more information.

  • 3: To attach additional information to the document package, select “Add document”. Either upload files from your computer or select files from Autodesk Docs.
    • Within a Budget Payment Application, the option to add from Cost Payment Applications is available, allowing users to collate associated expenses, attachments, and Supplier pay applications together for submission to the Owner.
  • 4: The three-dot menu next to the item provides additional capabilities (e.g. download Word doc, download PDF, re-generate, delete, rename, etc.)
  • 5: To open, download, or email a document package, select the three-dot menu at the package level.

Prediction and Analytics Capabilities

Construction IQ

  • Construction IQ is a built-in machine learning and AI functionality that leverages data across the entire BIM 360 platform.
  • Construction IQ sifts through millions of data points from your construction documents, issues, checklists, related meta-data and historical data, and analyzes it to identify and prioritize risks.
  • Construction IQ automatically classifies items and flag issues as “High Risk.”

 

  • “High Risk” issues are items that if left open, will likely lead to bigger more costly issues down the road.
    • EXAMPLE: if flashing was marked as missing on a window, the Issue would be flagged as “High Risk” to avoid bigger water leaking Issues.
  • View Construction IQ data through the “Risk” tab within the Insight module as well as by selecting cards tagged as “Construction IQ” in the Card Library.

 

About Construction IQ

Prediction & Analytics Blog

Executive Insight

  • With the ability to view company-wide performance data across multiple projects, executives and cross-project leaders can make more informed business decisions and gain visibility into overall risk assessment for current as well as future projects.
  • Invite users with “executive overview” permission to access this view. This is a separate Insight view geared towards Executives and cross project leaders only.

  • View cross project health across tabs:
    • Risk – shows projects with higher risk scores based on project data and Construction IQ capabilities.
    • Quality – overview of quality related checklist activity and conformance.
    • Safety – overview by project of safety related issues.

 

PRO TIP: Through the Risk tab in the Insight module, executives can get instant visibility into which projects have the highest risk levels each day. Assess the project risk overtime to see which projects remained in a “high risk” category over longer periods to determine which projects need executive level support.

Additional Capabilities

Account Admin

With the project administration tools in BIM 360, you can rest assured that your project information is in the right hands. Project admins can easily invite team members to the project and define their access levels on a project-by-project basis with a simple click. BIM 360 has two levels of administration to ensure security and control across your projects: Account admins and project admins. Only account admins can create new projects and assign additional account admins and project admins. Project admins can add and remove members, set permissions, and adjust project details.

Create a project

  • In the Account Admin module, select the Projects tab and click “Add.”
  • Enter project information and click “Save & Continue.”

 

Getting Started Guide

Create a Project

Activating Modules

  • Click “Activate” for the desired BIM 360 service.
  • Assign a project admin for each service. You can add multiple admins.
  • (Optional) For Document Management and Field you can copy existing project settings.
  • An email invitation will be sent to the assigned project admin(s). They will need to click the link to join the project.
  • Click “Finish.”

PRO TIP: You have to activate Document Management first, before you can activate other next-gen services.

Add members to directory

  • In the Account Admin module select the Members tab and click “Add.”
  • To add an individual member, select “Add People to the Member Directory.”
  • To add an account admin, select “Invite Account Admins.”
  • To import members from a list, select “Import Members by Spreadsheet.” For a first-time import, download and complete the member list template.

PRO TIP: You can change the default company and role later if necessary.

Adding members to a project & assigning access levels

  • In the “Project Admin” module, select the “Members” tab.
  • Click “Add” and use the search bar to search the member directory.
  • When you find the member, select them and click “Select.”
  • Add their company and role. Note: Role determines their access level to all BIM 360 services.
  • Click the icon(s) to overwrite the access level granted by
  • Click “Add to Project.”
  • Update existing access levels by clicking the grayed out icon(s).

 

 

Members & Access Levels

Setup Roles

PRO TIP: You can choose from a list of preset roles or create your own custom roles as well as configure the permission and access levels by each role.

Mobile Access

Construction doesn’t happen behind a desk. Teams need access to project documents and project management tools anytime, anywhere. With the BIM 360 mobile app, teams can execute construction quality and safety workflows, including creating or editing checklists, viewing RFIs, adding or tracking issues, and managing or creating drawing markups, directly from an Android or iOS device.

Download the BIM 360 app

  • Go to the App store or Google Play store on your mobile device to download the BIM 360 app.
  • The BIM 360 mobile app works with all other modules, including Document Management.

 

Get the iOS App


Get the Android App

 

PRO TIP: Stay up to date on mobile capabilities through the Autodesk Knowledge Network.

Mobile workflows

  • Several workflow capabilities can be accomplished using the BIM 360 mobile apps, including Checklists, Issue Management, RFI Tracking, Daily Logs, and Markups.
  • To see the differences in workflow capabilities for the BIM 360 and BIM 360 Docs apps, click the “BIM 360 Mobile Capabilities” link below.

BIM 360 Mobile Capabilities

About the iOS App

About the Android App

Offline sync

  • Teams are able to work on-site without Internet access.
  • Teams can also download individual documents and add markups and comments when working offline. Once back online, all changes will be synced back to the cloud.

 

Integration Partners

Get the most out of construction technology by integrating the software you already use with BIM 360. Built on an open and secure API platform, BIM 360 enables users to easily integrate with various other construction softwares, including drone technology, estimating and bid management, as well as safety management tools.